Supply chain interruptions are reaching critical levels and suspending work on projects. Shortages of bridge coating materials is the most recent area of concern and could be potentially catastrophic to unprepared contractors and owners. The inability to obtain materials may force painting contractors into a position where they cannot advance painting work, cannot retain painting crews, and may be asked to perform work in 2023 they had bid and scheduled for 2022.

What Can The Industry Do To Manage Risks?

Pre-bid, contractors must evaluate the availability of specified coatings and options for advance purchase and storage, confirm and lock-down material delivery timing, and account for any time and cost impacts associated with securing the materials.  Additionally, contractors may condition their performance obligations on the ability to obtain materials. Owners should consider breaking projects into small tranches, cooperating with contractors on advance purchase/storage, and be flexible and reasonable as additional disruptions and delays occur.  Owners should also take steps to ensure the bridge contractors are able to continue to operate, including providing change orders for increases in material, labor, and additional mobilization costs for work performed long after the initial schedule date. Ohio needs its skilled painting contractors in place and viable to mobilize and protect our bridge assets once materials are available.

For projects under contract, now more than ever it is imperative that contractors strictly follow the notification provisions in their contracts, including the ODOT C&MS, to preserve their entitlement to an extension of time. Under ODOT C&MS Section 108.06(B) Contractors are entitled to an excusable, non-compensable delay for: “Extraordinary delays in material deliveries the Contractor or its suppliers cannot foresee or avoid resulting from freight embargoes, government acts, or area-wide material shortages.” See ODOT C&MS 108.06(B)(3). However, the Contractor must notify the Engineer in compliance with ODOT C&MS Section 108.02(F). That means immediate oral notification and Written Early Notice within two days. Failure to follow these timelines can prejudice the contractor’s rights.

If you have questions or need assistance, our construction team is here to help.

Print:
Email this postTweet this postLike this postShare this post on LinkedIn
Photo of Aaron S. Evenchik Aaron S. Evenchik

Aaron S. Evenchik specializes in construction and real estate law, where he represents clients in both transactional and litigation matters. His cross-practice technique allows him to help resolve disputes innovatively and effectively. Aaron’s experience with transactions and handling multiple first chair litigation/arbitration matters…

Aaron S. Evenchik specializes in construction and real estate law, where he represents clients in both transactional and litigation matters. His cross-practice technique allows him to help resolve disputes innovatively and effectively. Aaron’s experience with transactions and handling multiple first chair litigation/arbitration matters enables him to better understand the goal of the deal and draft transactional documents to avoid problems and disputes. He advocates for and assists clients of all sizes to explore and close on properties, obtain zoning and to grow their businesses and meet their objectives.

Photo of Michael B. Pascoe Michael B. Pascoe

Michael B. Pascoe is a trial lawyer with experience in a wide range of commercial litigation representing both individuals and corporations in state and federal court. Mike routinely manages breach of contract claims, construction disputes, facilities management litigation, and business claims. He also…

Michael B. Pascoe is a trial lawyer with experience in a wide range of commercial litigation representing both individuals and corporations in state and federal court. Mike routinely manages breach of contract claims, construction disputes, facilities management litigation, and business claims. He also advises clients on contract negotiation, commercial lease negotiations and construction contracts. Mike frequently represents clients before the Occupational Safety and Health Review Commission.

Photo of Rob Remington Rob Remington

Rob Remington maintains a national legal practice encompassing a broad range of business disputes with a focus on complex commercial, construction and real estate litigation. Sophisticated clients with national litigation management experience describe Rob as a “class A” trial lawyer. He has a…

Rob Remington maintains a national legal practice encompassing a broad range of business disputes with a focus on complex commercial, construction and real estate litigation. Sophisticated clients with national litigation management experience describe Rob as a “class A” trial lawyer. He has a proven style when it comes to developing cases for trial, jury selection, and connecting with juries on even the most complex of issues. Rob’s practice includes acting as national construction counsel to a Fortune 100 contractor, a major international underground contractor, and the design and construction division of the largest ethanol manufacturer in the United States.